Stadium Armory Riders Get Bigger Station, Faster H Street Buses

Gold Line funding is still short, so Council action by around April 2027 decides whether buses roll in time for 2030.

Updated on Nov. 17, 2026 in Remote Work

Stadium Armory Riders Get Bigger Station, Faster H Street Buses

Live Poll

Do you think getting around your D.C. neighborhood will get easier over the next few years?

Riders heading to the new Commanders stadium at RFK will get a bigger Stadium Armory station, with a larger faregate mezzanine, a second mezzanine and two new elevators. Metro also released plans for a Gold Line bus rapid transit route with dedicated lanes on H Street NE.

Why it matters

Game days at the RFK site will put a lot of people through Stadium Armory at once, and the Gold Line is meant to make the trip between Farragut Square and Minnesota Avenue faster and more reliable. Metro says the Gold Line still needs Council money it has not yet received, and officials acknowledge traffic will be gridlocked at times under the plan.

Metro's projections put Farragut Square to Minnesota Avenue at 12-16 minutes on the Gold Line, down from 25-45 minutes today, and the Council has approved $305 million for Stadium Armory upgrades. Of the $80-85 million Gold Line Phase 1 budget, only $5 million has been approved, and the rest is still unfunded.

The players

Metro

The Washington Metropolitan Area Transit Authority released the Stadium Armory upgrade and Gold Line plans.

D.C. Council

The District's legislative body approved $305 million for Stadium Armory upgrades and must approve the remaining Gold Line money.

The details

Metro released renderings of the Stadium Armory upgrades, including a larger area outside the gates, a larger faregate mezzanine, a new second mezzanine and two new elevators. The work is part of $305 million the D.C. Council approved last month. For the Gold Line, Metro plans to run service between Farragut Square and the Minnesota Avenue stop, using dedicated bus lanes in the middle of H Street and other streets, with traffic signals programmed to prioritize buses. The work will leave one lane of regular car traffic in each direction on large parts of H Street NE, and Metro says curb space for parking and loading will be largely preserved.

Timeline

  1. Last month: the D.C. Council approved $305 million for Stadium Armory upgrades.

  2. Around April 2027: the Council needs to approve the Gold Line money for Metro to open on time.

  3. 2030: the stadium, the Gold Line and the NFL season are projected to open together.

The District View

The Council's $305 million vote for Stadium Armory is the funding already in place, and Metro's renderings show what that money will buy. The Gold Line is the part still waiting, with only $5 million of its $80-85 million Phase 1 budget approved so far.

If you commute along H Street NE or near Stadium Armory, expect a lane of car traffic in each direction on large stretches of the street while the work goes on, and possible gridlock at times. Game-day crowds at the new stadium will be routed through a bigger, better-equipped station once the upgrades are done.

The takeaway

Watch the Council's Gold Line budget vote around April 2027, because that approval decides whether the bus lanes open in time for the 2030 season. Plan for H Street detours and slower traffic during construction, and check Metro's service updates before you travel.

What happens next

The Council needs to approve the remaining Gold Line Phase 1 money by around April 2027 for Metro to open the line on time for the 2030 NFL season.

Further reading

For more on how commuting and transit are changing in the city, see our Remote Work coverage.

Live Poll

Do you think getting around your D.C. neighborhood will get easier over the next few years?